Friday, August 22, 2008

Germantown Av Construction through 8/29

Construction work on Germantown Avenue will be impacting the LTSP campus in several areas. If you have been around campus, you've seen that construction work is going on to remove the sidewalk and shoulder on the east (LTSP) side of the avenue from Gowen Avenue toward the refectory. Be sure to see Ltsp.edu/germantownave for routes to campus, and be sure to give yourself extra time to allow for temporary traffic stoppages.

PennDOT has reported that the project is on schedule for completion in November, but there will be impacts to campus through the fall. Note that there will always be access to campus, but you will find that some approaches will be detoured and may be temporarily closed. Subscribe to the weekly RSS feed at ltsptraffic.blogspot.com or watch email for weekly updates.

Here's the latest for the week ending August 29:

Weekend work and evening work: The final concrete pour in the current closure will take place beginning at 4 am Saturday, 8/23.

The contractors are hoping not to work over the Labor Day holiday weekend, but that depends upon their progress through 8/29.

Status of Other Aspects of the Project:

McPherson Street will open to traffic on Monday, August 25th. The contractors will open up parts of Germantown Avenue within the current closure as the concrete and cobblestones cure.

Gowen Avenue closure and detours: The intersection of Gowen Avenue will be closed to through traffic for the next 3 1/2 weeks. Motorists coming from Stenton on Gowen will be detoured at Ardleigh Street (to reach the Reed lot you will be considered local traffic and should be able to pass).

Exiting Reed lot
, you will need to turn right out of the driveway. Take the Ardleigh detour - right onto Ardleigh, right onto Mt. Airy, left onto Germantown - to reach Germantown Avenue southbound. To reach northbound Germantown, turn right out of the driveway, turn left onto Boyer, then left at Roumfort and right onto Germantown. Be careful, there are many residents in the area.

Motorists coming north on Germantown Avenue will be forced to make a right turn at Gowen, allowing you to reach the Reed lot if going northbound on Germantown (but see instructions on exiting Reed lot).

Bryan Street (off west Allens Lane) will be open to two-way traffic temporarily for the benefit of residents of West Gowen Avenue, Gowen Circle and the 7300 block of Bryan.

SAVE THE AVENUE COALITION: Remember that all businesses remain open during the construction project.Visit the Save the Avenue website, www.savetheave.org, for updated information, including special promotions and information on how you can support our merchants.

No comments: