Work continues on Germantown Avenue, with some work close to campus. Work also continues on the renovations of the LTSP chapel, which has the sidewalk on Germantown Avenue closed from south edge of campus to Allens Lane. Access to the LTSP campus remains open to both the Brossman and Reed parking lots. See Ltsp.edu/germantownave for alternate routes to campus and other information.

WORK INSIDE THE CLOSURE:

The current closure continues from the south driveway of the Trolley Car Diner through the south entrance to the New Covenant campus. Workers will continue to lay cobblestones in the closure area are weeks. The current road closure will last for several more weeks. Access to the Trolley Car Diner and New Covenant Campus is from the north.

WORK OUTSIDE THE CLOSURE:

Work at the Gowen Avenue intersection will continue al least through the end of this week. The intersection will be closed in the evenings and into the night as it has been recently with detours posted. There may be temporary traffic stoppages at the intersection during daytime hours with police directing traffic. Delays will be minimal.

There is continued work around the bridge near the intersection of Cresheim Valley Drive and Germantown Avenue with minimal impact on motorists and pedestrians.

No comments: