Tuesday, November 4, 2008
All Routes to LTSP are Open
Sunday, October 26, 2008
Germantown Av through November2
Through the end of this week, construction continues directly in front of the LTSP campus on Germantown Avenue, and the Allens Lane intersection and main entrance on Germantown Avenue remain closed to all traffic. The Brossman and Wiedemann lots can be accessed using the new driveway south of the chapel - there is a road closed sign along with a flag person on Germantown Avenue at Mt. Airy Avenue - you can pass through that area and access the driveway, follow the signs. Note that construction work may cause temporary traffic stoppages in this area. See alternate directions to campus at Ltsp.edu/germantownave. Here are further details:
CURRENT DETOURS REMAIN
- PennDOT's work schedule will keep the Avenue in front of campus closed through the month, but once open the road work will be substantially done. At that point, tentatively by the end of the week, intersections and campus entrances with be open and passable, though finishing work may cause delays or temporary closures. Detours are substantially unchanged.
- Allens Lane eastbound is detoured at Cresheim Road (at the Allens Lane train station). Local traffic only, including access to Wawa and Valley Green Bank parking lots. PLEASE DO NOT GO BEYOND CRESHEIM ROAD UNLESS YOU ABSOLUTELY HAVE TO. To access the Brossman and Wiedemann lots if you're approaching on Allens Lane and miss the detour to Germantown, turn right onto Bryan Street, then left onto Durham Street and left onto Germantown Avenue and continue on Germantown through the Mt. Airy Avenue road closed point and turn right into the driveway south of the chapel.
- Germantown Avenue northbound is closed at East Mt. Airy Avenue. The posted detour actually begins at Mt. Pleasant Avenue. Local traffic to LTSP's new entry south of the chapel is possible, but there may be temporary shutdowns past the road closed signs due to construction. You can also turn right onto East Mt. Airy Avenue, then left onto Boyer Street and left onto Gowen Avenue to reach the Reed lot.
- Germantown Avenue southbound is open to Gowen Avenue. You can turn left and access the Reed lot, or turn right and detour around the construction - Gowen turns into Bryan Street, remain on Bryan, cross Mt. Airy Avenue (still closed at Germantown) and turn left at the next street, Nippon Street, which will take you to Germantown Avenue, where you can turn left and then right into the new driveway at the chapel/plaza.
- Gowen Avenue westbound is open to Germantown Avenue. You may access the Reed lot and Brewer's Outlet this way. At Germantown Avenue you must either continue on Gowen westbound or turn right onto northbound Germantown.
CURRENT STATUS OF PROJECT
To keep the project on schedule, a second evening shift (until 11 pm) may be used. The last track has been laid and concrete poured, with cobblestone and sidewalk work, including the apron at the main entrance to campus, to be done early this week. Plans are for the Allens Lane intersection and campus entrance to be reopened for vehicles and pedestrian traffic late in the week, dependent on weather conditions. Finishing work will continue through November but will not cause traffic problems.- The Allens Lane intersection is closed and will reopen toward the end of October.
- Work at Mermaid Lane intersection continues. Flower shop is accessible, as are businesses in the mall across the street. There will continue to be lane changes here but access to Chestnut Hill will not be closed.
PEDESTRIAN ACCESS
Pedestrians may use the east side of Germantown Avenue going north from Mermaid Lane. Please follow pedestrian directional signs throughout the construction zone. Walkways in front of campus on Germantown will continue to be obstructed and directions will change as the work progresses.
Monday, October 20, 2008
Germantown Av Construction through 10/27
Through the end of October, construction continues directly in front of the LTSP campus on Germantown Avenue, and the Allens Lane intersection and main entrance on Germantown Avenue remain closed to all traffic. The Brossman and Wiedemann lots can be accessed using the new driveway south of the chapel - there is a road closed sign along with a flag person on Germantown Avenue at Mt. Airy Avenue - you can pass through that area and access the driveway, follow the signs. Note that construction work may cause temporary traffic stoppages in this area. See alternate directions to campus at Ltsp.edu/germantownave. Here are further details:
CURRENT DETOURS REMAIN
- PennDOT's work schedule will keep the Avenue in front of campus closed through the month, but once open the road work will be substantially done. At that point, with exact date dependent on weather and work progress, intersections and campus entrances with be open and passable, though finishing work may cause delays or temporary closures. Detours are substantially unchanged.
- Allens Lane eastbound is detoured at Cresheim Road (at the Allens Lane train station). Local traffic only, including access to Wawa and Valley Green Bank parking lots. PLEASE DO NOT GO BEYOND CRESHEIM ROAD UNLESS YOU ABSOLUTELY HAVE TO. To access the Brossman and Wiedemann lots if you're approaching on Allens Lane and miss the detour to Germantown, turn right onto Bryan Street, then left onto Durham Street and left onto Germantown Avenue and continue on Germantown through the Mt. Airy Avenue road closed point and turn right into the driveway south of the chapel.
- Germantown Avenue northbound is closed at East Mt. Airy Avenue. The posted detour actually begins at Mt. Pleasant Avenue. Local traffic to LTSP's new entry south of the chapel is possible, but there may be temporary shutdowns past the road closed signs due to construction. You can also turn right onto East Mt. Airy Avenue, then left onto Boyer Street and left onto Gowen Avenue to reach the Reed lot.
- Germantown Avenue southbound is detoured at East Roumfort Road. You may still access Cresheim Cottage Cafe and dentist's office this way. Traffic is forced to turn right on West Gowen Avenue - you cannot turn left to access the Reed lot.
- Gowen Avenue westbound is open to Germantown Avenue. You may access the Reed lot and Brewer's Outlet this way. At Germantown Avenue you must either continue on Gowen westbound or turn right onto northbound Germantown.
CURRENT STATUS OF PROJECT
To keep the project on schedule, a second evening shift (until 11 pm) may be used, and as the roadway is prepared, concrete pouring will begin as early as 4:30 am later in the week. The last track is being laid north of the main campus entrance, and more concrete is to be poured, along with cobblestone and sidewalk work. This is dependent on weather conditions. Reminder: the entrance at the chapel is temporarily 2-way continuing to and from the Brossman lot. This is the temporary exit from Brossman and Wiedemann lots to the street, as well as being the entrance. Be cautious when using this driveway in either direction.- The Allens Lane intersection is closed and will reopen toward the end of October.
- Work at Mermaid Lane intersection continues. Flower shop is accessible, as are businesses in the mall across the street. There will continue to be lane changes here but access to Chestnut Hill will not be closed.
- Weekend, evening and night work will take place: concrete pours may begin at 4:30 am.
PEDESTRIAN ACCESS
Pedestrians may use the east side of Germantown Avenue going north from Mermaid Lane. Please follow pedestrian directional signs throughout the construction zone. Walkways in front of campus on Germantown will continue to be obstructed and directions will change as the work progresses.
Monday, October 13, 2008
Germantown Av update through 10/17
For the next week several weeks, construction continues directly in front of the LTSP campus on Germantown Avenue, and the Allens Lane intersection and main entrance on Germantown Avenue remain closed to all traffic. The Brossman and Wiedemann lots can be accessed using the new driveway south of the chapel - there is a road closed sign along with a flag person on Germantown Avenue at Mt. Airy Avenue - you can pass through that area and access the driveway, follow the signs. Note that construction work may cause temporary traffic stoppages in this area. See alternate directions to campus at Ltsp.edu/germantownave. Here are further details:
CURRENT DETOURS REMAIN
- PennDOT has adjusted the work schedule to make the work more efficient. This will keep the Avenue in front of campus closed through the month, but once open the road work will be substantially done. At that point, intersections and campus entrances with be open and passable, though finishing work may cause delays or temporary closures. Detours are substantially unchanged.
- Allens Lane eastbound is detoured at Cresheim Road (at the Allens Lane train station). Local traffic only, including access to Wawa and Valley Green Bank parking lots. PLEASE DO NOT GO BEYOND CRESHEIM ROAD UNLESS YOU ABSOLUTELY HAVE TO. To access the Brossman and Wiedemann lots if you're approaching on Allens Lane and miss the detour to Germantown, turn right onto Bryan Street, then left onto Durham Street and left onto Germantown Avenue and continue on Germantown through the Mt. Airy Avenue road closed point and turn right into the driveway south of the chapel.
- Germantown Avenue northbound is closed at East Mt. Airy Avenue. The posted detour actually begins at Mt. Pleasant Avenue. Local traffic to LTSP's new entry south of the chapel is possible, but there may be temporary shutdowns past the road closed signs due to construction. You can also turn right onto East Mt. Airy Avenue, then left onto Boyer Street and left onto Gowen Avenue to reach the Reed lot.
- Germantown Avenue southbound is detoured at East Roumfort Road. You may still access Cresheim Cottage Cafe and dentist's office this way. Traffic is forced to turn right on West Gowen Avenue - you cannot turn left to access the Reed lot.
- Gowen Avenue westbound is open to Germantown Avenue. You may access the Reed lot and Brewer's Outlet this way. At Germantown Avenue you must either continue on Gowen westbound or turn right onto northbound Germantown.
CURRENT STATUS OF PROJECT
To keep the project on schedule, work will continue into a second evening shift (until 11 pm) through part of the week, and as the roadway is prepared, concrete pouring will begin as early as 4:30 am later in the week. This is dependent on weather conditions. Reminder: the entrance at the chapel is temporarily 2-way continuing to and from the Brossman lot. This is the temporary exit from Brossman and Wiedemann lots to the street, as well as being the entrance. Be cautious when using this driveway in either direction.- The Allens Lane intersection is closed and will not reopen for two more weeks.
- The Gowen Avenue intersection will reopen around Wednesday October 15. Germantown Avenue southbound will remain closed.
- Work at Mermaid Lane intersection continues. Flower shop is accessible, as are businesses in the mall across the street. There will continue to be lane changes here but access to Chestnut Hill will not be closed.
- Weekend, evening and night work will take place: all concrete pours will begin at 4:30 am.
PEDESTRIAN ACCESS
Pedestrians may use the east side of Germantown Avenue going north from Mermaid Lane. Please follow pedestrian directional signs throughout the construction zone. Walkways in front of campus on Germantown will continue to be obstructed and directions will change as the work progresses.
Monday, October 6, 2008
Germantown Av update to 10/10
Construction continues directly in front of the LTSP campus on Germantown Avenue, and the Allens Lane intersection and main entrance on Germantown Avenue remain closed to all traffic. The Brossman and Wiedemann lots can be accessed using the new driveway south of the chapel - there is a road closed sign along with a flag person on Germantown Avenue at Mt. Airy Avenue - you can pass through that area and access the driveway, follow the signs. Note that construction work may cause temporary traffic stoppages in this area. See alternate directions to campus at Ltsp.edu/germantownave. Here are further details:
CURRENT DETOURS REMAIN
- Allens Lane eastbound is detoured at Cresheim Road (at the Allens Lane train station.) Local traffic only, including access to Wawa and Valley Green Bank parking lots. PLEASE DO NOT GO BEYOND CRESHEIM ROAD UNLESS YOU ABSOLUTELY HAVE TO. To access the Brossman and Wiedemann lots if you're approaching on Allens Lane and miss the detour to Germantown, turn right onto Bryan Street, then left onto Durham Street and left onto Germantown Avenue and continue on Germantown through the Mt. Airy Avenue road closed point and turn right into the driveway south of the chapel.
- Germantown Avenue northbound is closed at East Mt. Airy Avenue. The posted detour actually begins at Mt. Pleasant Avenue. Local traffic to LTSP's new entry south of the chapel is possible, but there may be temporary shutdowns past the road closed signs due to construction. You can also turn right onto East Mt. Airy Avenue, then left onto Boyer Street and left onto Gowen Avenue to reach the Reed lot.
- Germantown Avenue southbound is detoured at East Roumfort Road. You may still access Cresheim Cottage Cafe and dentist's office this way. Traffic is forced to turn right on West Gowen Avenue - you cannot turn left to access the Reed lot.
- Gowen Avenue westbound is open to Germantown Avenue. You may access the Reed lot and Brewer's Outlet this way. At Germantown Avenue you must either continue on Gowen westbound or turn right onto northbound Germantown.
CURRENT STATUS OF PROJECT
To keep the project on schedule, work will continue into a second evening shift (until 11 pm) through part of the week, and as the roadway is prepared, concrete pouring will begin as early as 4:30 am later in the week. This is dependent on weather conditions. Reminder: the entrance at the chapel is temporarily 2-way continuing to and from the Brossman lot. This is the temporary exit from Brossman and Wiedemann lots to the street, as well as being the entrance. Be cautious when using this driveway in either direction.- The Allens Lane intersection is closed and will not reopen for two more weeks.
- The Gowen Avenue intersection will reopen by Friday October 10th. Germantown Avenue southbound will remain closed.
- Work at Mermaid Lane intersection continues. Flower shop is accessible, as are businesses in the mall across the street. There will continue to be lane changes here but access to Chestnut Hill will not be closed.
- Weekend, evening and night work will take place: all concrete pours will begin at 4:30 am.
PEDESTRIAN ACCESS
Pedestrians may use the east side of Germantown Avenue going north from Mermaid Lane. Please follow pedestrian directional signs throughout the construction zone. Walkways in front of campus on Germantown will continue to be obstructed and directions will change as the work progresses.
Friday, September 26, 2008
Germantown Ave. Update - 9/26
Here's what is projected through October 2:
Germantown Ave., Main Entrance, Brossman and Wiedemann Lot access:
Construction is occurring directly in front of campus from Gowen Avenue south along the entire campus frontage. Temporary roadway is expected to be installed by Thursday, 10/1, and construction will proceed behind barricades with provision for traffic to pass. Be prepared for temporary closures and stoppages as the work progresses through the fall.
Of special note: Germantown Avenue is barricaded northbound at Mt. Airy Avenue, though the flagger at the barricade will allow passage to the new campus entrance on the south side of the chapel at the new plaza. Use caution when you enter and proceed to the Brossman parking lot. Note there is an orange directional sign at this entrance. THIS DRIVEWAY IS TEMPORARILY 2-WAY - drive slowly and cautiously both when entering and leaving campus, the drive is only wide enough for one vehicle to pass. The main campus entrance on Germantown Avenue is temporarily closed.
Allens Lane is closed at Germantown Avenue. A detour is posted - see Ltsp.edu/germantownave for other routes to campus from the west. Note that the Wawa entrance/exit to Germantown Avenue is also closed, so you can't cut through the Wawa lot to get to the new south entrance on Germantown.
Gowen Avenue:
Gowen is now open through from east to west side of Germantown Avenue, and you can turn north on Germantown Avenue, but not south. If you do come this way to get to the Germantown Avenue entrances to campus, you will need to continue through the intersection, then continue through side street until you can turn left at a street past Allens Lane. Best to park in the Reed lot.
Our business neighbors continue to suffer from the construction project. Consider ways you can patronize them and help keep the neighborhood vital. See savetheave.org for more information.
Tuesday, September 23, 2008
Construction Update - Entrance Changes - 9/23

Special Note:
While the construction continues on the west side of Germantown Avenue across from campus, starting Tuesday 9/23 there will be periodic closures of Germantown from Allens Lane north, including the LTSP main entrance on Germantown Avenue. By 9/25, this will be a complete closure that is expected to last 2-3 weeks.
To reach the Brossman, Wiedemann and Hagan parking areas, take Germanto
wn Avenue from the south. There is a just-opened entrance at the south end of campus, next to the plaza construction at the chapel. PennDOT has provided a sign at this location to direct you into the entrance, and flaggers will be in the area. Use caution as you drive past the chapel as construction workers continue to work on the new plaza and chapel exterior. THIS IS ALSO THE ROUTE TO EXIT THESE PARKING AREAS, SO BE DRIVE SLOWLY AND BE ALERT FOR EXITING VEHICLES.With these closures, you may prefer to use the Reed lot, which you can access from the east using Gowen Avenue.
See Ltsp.edu/germantownave for maps and alternate routes to campus.
Updated to include entrance photos and additional information.
Monday, September 15, 2008
Germantown Av construction through 9/20
Here is specific information for work during the coming week:
Gowen Avenue intersection will be tied up until finishing work is done. Subsequently, Gowen will be opened partially from the north (Chestnut Hill) to allow traffic to Cresheim Cottage Cafe and West Gowen Avenue. You will NOT be able to turn left onto Gowen from the north. Access from the north to East Gowen and the Reed lot is only from the Stenton end of East Gowen. Motorists coming from Stenton on Gowen are detoured left at Ardleigh Street to right on Mt. Airy Avenue to Germantown Avenue; turn right at Germantown to access the Brossman parking lot through the main campus entrance. Motorists continuing north on Germantown Avenue will be forced to make a right turn onto East Gowen, which allows you to access the Reed lot.
Construction will continue in the Allens Lane intersection across from the LTSP campus. There will be alternate traffic patterns and congestion on both Germantown and Allens Lane. Be careful to keep right at all times since traffic remains 2 way. There are no turning lanes or shoulders while the alternate traffic patterns are on place.
Mermaid Lane, Chestnut Hill: Crews are beginning prep work on the sidewalks at Mermaid Lane. PEDESTRIAN ACCESS WILL REMAIN, with pedestrians routed along the east side of the sidewalk to the flower shop at the trolley turn-around.
SAVE THE AVENUE COALITION: Remember that all businesses remain open during the construction project. Visit the Save the Avenue Web site, www.savetheave.org, for updated information, including special promotions and information on how you can support our community's merchants.
Friday, September 5, 2008
Germantown Av construction through 9/13
Here is specific information for work during the coming week:
No work scheduled Saturday 9/6 due to the anticipated heavy rains. Work resumes Monday 9/8.
Gowen Avenue intersection will be tied up for the next week as track is laid and finishing work is done. Subsequently, Gowen will be opened partially from the north (Chestnut Hill) to allow traffic to Cresheim Cottage Cafe and West Gowen Avenue. Access from the north to East Gowen and the Reed lot is only from the Stenton end of East Gowen. Motorists coming from Stenton on Gowen are detoured left at Ardleigh Street to right on Mt. Airy Avenue to Germantown Avenue; turn right at Germantown to access the Brossman parking lot through the main campus entrance. Motorists continuing north on Germantown Avenue will be forced to make a right turn onto East Gowen, which allows you to access the Reed lot.
Construction will continue in the Allens Lane intersection across from the LTSP campus. There will be alternate traffic patterns and congestion on both Germantown and Allens Lane. Be careful to keep right at all times since traffic remains 2 way. There are no turning lanes or shoulders while the alternate traffic patterns are on place.
Mermaid Lane, Chestnut Hill: By the middle/end of the week of 9/8, crews will begin prep work on the sidewalks at Mermaid Lane. PEDESTRIAN ACCESS WILL REMAIN, with pedestrians routed along the east side of the sidewalk to the flower shop at the trolley turn-around.
SAVE THE AVENUE COALITION: Remember that all businesses remain open during the construction project. Visit the Save the Avenue Web site, www.savetheave.org, for updated information, including special promotions and information on how you can support our community's merchants.
Friday, August 22, 2008
Germantown Av Construction through 8/29
PennDOT has reported that the project is on schedule for completion in November, but there will be impacts to campus through the fall. Note that there will always be access to campus, but you will find that some approaches will be detoured and may be temporarily closed. Subscribe to the weekly RSS feed at ltsptraffic.blogspot.com or watch email for weekly updates.
Here's the latest for the week ending August 29:
Weekend work and evening work: The final concrete pour in the current closure will take place beginning at 4 am Saturday, 8/23.
The contractors are hoping not to work over the Labor Day holiday weekend, but that depends upon their progress through 8/29.
Status of Other Aspects of the Project:
McPherson Street will open to traffic on Monday, August 25th. The contractors will open up parts of Germantown Avenue within the current closure as the concrete and cobblestones cure.
Gowen Avenue closure and detours: The intersection of Gowen Avenue will be closed to through traffic for the next 3 1/2 weeks. Motorists coming from Stenton on Gowen will be detoured at Ardleigh Street (to reach the Reed lot you will be considered local traffic and should be able to pass).
Exiting Reed lot, you will need to turn right out of the driveway. Take the Ardleigh detour - right onto Ardleigh, right onto Mt. Airy, left onto Germantown - to reach Germantown Avenue southbound. To reach northbound Germantown, turn right out of the driveway, turn left onto Boyer, then left at Roumfort and right onto Germantown. Be careful, there are many residents in the area.
Motorists coming north on Germantown Avenue will be forced to make a right turn at Gowen, allowing you to reach the Reed lot if going northbound on Germantown (but see instructions on exiting Reed lot).
Bryan Street (off west Allens Lane) will be open to two-way traffic temporarily for the benefit of residents of West Gowen Avenue, Gowen Circle and the 7300 block of Bryan.
SAVE THE AVENUE COALITION: Remember that all businesses remain open during the construction project.Visit the Save the Avenue website, www.savetheave.org, for updated information, including special promotions and information on how you can support our merchants.
Friday, August 8, 2008
Germantown Av construction through 4/16
Weekend work and evening work: There will be work at the Gowen Avenue intersection the evening of 8/8 until 11 and likely Saturday, 8/9 as well. There will be work from 4 am until 7 am the week of 8/11 inside the closure as concrete is poured There might also be activity beginning at 11 pm or midnight inside the closure. This will include lights.
Work from Nippon to Allens Lane - in front of campus - is coming Monday 8/18: There will be work on the west side sidewalk area from Nippon to Allens Lane, across from campus, the week of the 18th. This will result in lane shifts during the daytime. Businesses and campus will be accessible, but the turn into campus may be tight.
SAVE THE AVENUE COALITION: Remember that all businesses remain open during the construction project.Visit the Save the Avenue website, www.savetheave.org, for updated information, including special promotions and information on how you can support our merchants.
Wednesday, August 6, 2008
Germantown Av. - Week of August 5
Construction this week: The work at the Gowen Avenue intersection continues, with lane closures and temporary traffic stoppages during construction hours. Traffic moves, but the space is tight. There will be work from 7 am until 11 pm Wednesday-Friday, August 6-8, inside the closure.
This closure is scheduled to open at or near the begining of September. At that time, the work will move to the Gowen Avenue intersection. Also in early September, major work will commence in the Germantown Avenue/Mermaid Lane area at the northernmost part of the project. In both cases, PennDOT and the construction company are working on a plan to reduce the impact on motorists and pedestrians, as well as to affected businesses. Details will be provided as they become available.
FOR STUDENTS RETURNING TO CAMPUS HOUSING:
The construction at the Gowen Avenue intersection will present challenges for maneuvering large vehicles such as self-move trucks. Plan your approach to campus and parking with large vehicles accordingly:
WIEDEMANN RESIDENTS should approach campus from the south along Germantown Avenue to avoid the construction. There are construction signs in the shoulder of the roadway, and the main campus entrance requires a hard right turn; the drive right curves a bit once you enter, followed by a left past the Muhlenberg statue to enter the Wiedemann lot. Take care to avoid the stone pillars on the wall on either side of the entrance, and plan your turn to consider the obstacles in the roadway and the turn once you enter campus.
PERIPHERAL HOUSING RESIDENTS should approach from Stenton Avenue, taking Gowen to the Reed Lot entrance or to stop in front of the houses on Gowen. This will avoid the construction at Gowen and Germantown Avenues. The Reed entrance is tight (and has two-way traffic) and curves to the left. Also note that the Reed lot itself is one way once you enter the lot - make an immediate right and circulate counter-clockwise through the lot. Take care on entering and exiting Reed as residents park on both sides of Gowen.
View or download the campus map online at ltsp.edu/campus/campus.htm. See ltsp.edu/germantownave for directions to campus from different approaches, as well as an area map. Construction at the Gowen intersection has been stopping around 4 pm, though with work in the closure area continuing through to 11 pm there may be workers and vehicles around the intersection.
SAVE THE AVENUE COALITION: Remember that all businesses remain open during the construction project.Visit the Save the Avenue website, www.savetheave.org, for updated information, including special promotions and information on how you can support our merchants.
Friday, July 25, 2008
Germantown Av. Construction to 8/1
WORK INSIDE CLOSURE:
Weekend work: There will be work inside the closure this Saturday, 7/26.
Pedestrian Access around the closure: The week of 7/28, there will be sidewalk laid on the west (New Covenant Church/Cresheim Cottage Cafe) side of the closure. This could result in pedestrian access through the closure being rerouted somewhat. However, there will be no loss of pedestrian access. Please note that Cresheim Cottage Cafe will remain open throughout this period, although access might be changed a bit as the sidewalk directly outside is rebuilt.
HEAD'S UP FOR FUTURE WORK:
In early September, major work will commence in the Germantown Avenue/Mermaid Lane area at the northernmost part of the project (in lower Chestnut Hill). In addition, the construction project will move more fully into the Gowen Avenue intersection soon after that. In both cases, PennDOT and the construction company are working to reduce the impact on
motorists and pedestrians. Details will be provided as they become available.
SAVE THE AVENUE COALITION: Remember that all businesses remain open during the
construction project.Visit the Save the Avenue website, www.savetheave.org, for
updated information, including special promotions and information on how you can
support our merchants.
Tuesday, July 15, 2008
Germantown Av Construction through July 20
CLOSURE WILL BE MOVED:
On Tuesday, July 15th, workers will be moving the closure to the south side of Roumfort Road: Roumfort itself will then be open to traffic from the north. McPherson Street will be closed at this point.
Beginning Tuesday, construction will proceed on day and evening shifts for a week. There will be no work the weekend of July 19. This closure is expected to last for about 6 weeks. Access to the Trolley Car Diner and New Covenant Campus remains from the north.
WORK OUTSIDE THE CLOSURE:
Work at the Gowen Avenue intersection will continue. Gradually, the sewer work will be moving south along Germantown Avenue ahead of the work inside the closure. Expect some lane closures and temporary stoppages at and near the intersection at times.
SAVE THE AVENUE COALITION: Remember that all businesses remain open during the construction project.Visit the Save the Avenue Web site, www.savetheave.org, for updated information, including special promotions and information on how you can support our merchants.
Monday, July 7, 2008
Germantown Av. update through 7/12
WORK INSIDE THE CLOSURE:
The current closure continues from the south driveway of the Trolley Car Diner through the south entrance to the New Covenant campus. Workers will continue to lay cobblestones in the closure area are weeks. The current road closure will last for several more weeks. Access to the Trolley Car Diner and New Covenant Campus is from the north.
WORK OUTSIDE THE CLOSURE:
Work at the Gowen Avenue intersection will continue al least through the end of this week. The intersection will be closed in the evenings and into the night as it has been recently with detours posted. There may be temporary traffic stoppages at the intersection during daytime hours with police directing traffic. Delays will be minimal.
There is continued work around the bridge near the intersection of Cresheim Valley Drive and Germantown Avenue with minimal impact on motorists and pedestrians.
Friday, June 13, 2008
Germantown Av. Construction through 6/22
GERMANTOWN AVENUE CLOSURE:
The closure continues in the area south of the Trolley Car Diner. Access to the diner and New Covenant campus is from the north (Chestnut Hill). Workers are working a single day shift for a week or so, with new curbstone, trolley tracks and sidewalks coming through the week, and concrete for the track structure to be poured the week of June 23. This work is scheduled to continue for the next several weeks.
WORK OUTSIDE THE CLOSURE:
Sewer work outside the closure from McPherson Street to Gowen Avenue will continue though the end of June. The barrier will be moved south to just below Gowen. PECO will continue work on the west sidewalk from Allens Lane to Nippon Street (in the area of Wawa and the bank) this week. This may require lane shifts. Note that LTSP's chapel construction has closed the sidewalk in front of the chapel.
Construction on the Gowen Avenue intersection is expected to begin at the end of June or the beginning of July.
SAVE THE AVENUE COALITION: Remember that all businesses remain open during the construction project. Visit the Save the Avenue website, www.savetheave.org, for updated information, including special promotions and information on how you can support our merchants.
Wednesday, June 11, 2008
Germantown Av. construction through 6/14
GERMANTOWN AVENUE CLOSURE:
The closure continues in the area south of the Trolley Car Diner. Access to the diner and New Covenant campus is from the north (Chestnut Hill). Workers are working a single day shift for a week or so. This work is scheduled to continue for the next several weeks.
WORK OUTSIDE THE CLOSURE:
Sewer work outside the closure from McPherson Street to Gowen Avenue will continue though the end of June. The barrier will be moved south to just below Gowen. PECO will be doing work on the west sidewalk from Allens Lane to Nippon Street (in the area of Wawa and the bank) for a few days this week. This may require lane shifts. Note that LTSP's chapel construction has closed the sidewalk in front of the chapel.
Construction on the Gowen Avenue intersection is expected to begin at the end of June or the beginning of July.
SAVE THE AVENUE COALITION: Remember that all businesses remain open during the construction project. Visit the Save the Avenue website, www.savetheave.org, for updated information, including special promotions and information on how you can support our merchants.
Monday, June 2, 2008
Germantown Av. Construction through 6/7
GERMANTOWN AVENUE CLOSURE:
The closure is in the area south of the Trolley Car Diner. Access to the diner and New Covenant campus is from the north (Chestnut Hill). This work is scheduled to continue for the next 7 weeks.
WORK OUTSIDE THE CLOSURE:
Until June 21 or thereabouts, there will be sewer work outside the closure from McPherson Street to Gowen Avenue. This work will take place behind the existing barrier. Also, there will be continued work on the old stone bridge just south of the intersection of Germantown Avenue with Cresheim Valley Road, as well as on the fountain. This work will not affect traffic. PECO will be doing work on the west sidewalk from Allens Lane to Nippon Street (in the area of Wawa and the bank) for a few days this week. This may require lane shifts.
SAVE THE AVENUE COALITION: Remember that all businesses remain open during the construction project.Visit the Save the Avenue website, www.savetheave.org, for updated information, including special promotions and information on how you can support our merchants.
Tuesday, May 27, 2008
Germantown Ave Construction through 5/31
CLOSURE UPDATE
New Covenant Church and Trolley Car Diner traffic are being routed from Cresheim Valley Drive. Thus, both the Trolley Car Diner and New Covenant will be accessible from Chestnut Hill. There is walking access through the construction area, making the Diner and Chestnut Hill accessible from LTSP and Mt. Airy along Germantown Avenue by foot.
The next closure is from the New Covenant Church driveway south to just before McPherson, including the intersection of Roumfort Road. The contract calls for this closure to last for 8 weeks.
WORK OUTSIDE THE CLOSURES:
For the next two weeks, traffic will be moved to the west curbline as work continues outside the closure on the east side of Germantown Avenue down to Gowen Avenue.
Also, there will be continued work on the old stone bridge just south of the intersection of Germantown Avenue with Cresheim Valley Road, as well as on the fountain. This work will not affect traffic.
"MOVE ON DOWN BLOCK PARTY"
You are cordially invited to a "Move On Down Block Party" to celebrate progress on the reconstruction project -- Saturday, May 31st from noon -- 2 pm on Germantown Avenue from Cresheim Valley Road to the Trolley Car Diner. Enjoy free water ice courtesy of Trolley Car Diner, enter for a chance to win a high-end DVD player and free video rentals from TLA Video, and savor delicious treats and beer from Night Kitchen and Brewer's Outlet. New offerings are being added as we speak, so that's not all! All are welcome!
Friday, May 16, 2008
Germantown Av construction through 5/23
NEXT WEEK AND THE CLOSURES:
It is again possible to walk between Mt. Airy and Chestnut Hill, though the sidewalk may be redirected around the construction closure.
The week of 5/18 is a transition week for the closures. The current closure will be opened, based on current plans, and the next closure will begin on or around May 21. At that point, access to the Trolley Car Diner will be from Chestnut Hill, and access to New Covenant Campus will be from Mt. Airy. The Diner plans to put up signage to direct traffic when that transition occurs.
The closure on or around May 21 will be from the southernmost entrance to Trolley Car Diner to just north of McPherson Street (all north of LTSP). Rain might delay this transition somewhat, so please be flexible in getting to where you need to go. This closure is anticipated to last for 8 weeks. There will be pedestrian access throughout.
WORK OUTSIDE THE CLOSURES:
Right now, work continues in the McPherson intersection area to prepare for the change in closures. Storm and sewage work will then continue on the east side up to Gowen Avenue. This work cannot be done in the rain, so precipitation might delay progress.
Also, there will be continued work on the old stone bridge just south of the intersection of Germantown Avenue with Cresheim Valley Road, as bridge repairs are finished and the green area is restored. This work will not affect traffic, but there will be vehicles parked on the shoulder at some points.
SAVE THE AVENUE COALITION: Remember that all businesses remain open during the construction project. Visit the Save the Avenue Web site, www.savetheave.org, for updated information, including special promotions and information on how you can support the community's merchants.